CEQA appeal: superior court clerk certifies clerk's transcript within 60 days after designation filed
60 days after date the notice designating the clerk's transcript was filed, under Cal. Pub. Res. Code 21167.6(g).
Rule text
(g) The clerk of the superior court shall prepare and certify the clerk's transcript on appeal not later than 60 days from the date that the notice designating the papers or records to be included in the clerk's transcript was filed with the superior court, if the party or parties pay any costs or fees for the preparation of the clerk's transcript
Calculate this deadline
Deadline
Tuesday, January 5, 2027
- Trigger (Date the notice designating the clerk's transcript was filed): Friday, November 6, 2026.
- Exclude the trigger day and count 60 calendar days: Tuesday, January 5, 2027.
Rules applied
Cal. Pub. Res. Code 21167.6(g)
(g) The clerk of the superior court shall prepare and certify the clerk's transcript on appeal not later than 60 days from the date that the notice designating the papers or records to be included in the clerk's transcript was filed with the superior court, if the party or parties pay any costs or fees for the preparation of the clerk's transcriptOfficial source
Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)
CCP 12: "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded." CCP 12a(a): "If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays." Gov. Code 6707: "When the last day for filing any instrument or other document with a state agency falls upon a Saturday or holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed." FRCP 6(a): "The following rules apply in computing any time period specified in these rules, in any local rule or court order, or in any statute that does not specify a method of computing time. (1) ... (A) exclude the day of the event that triggers the period; (B) count every day, including intermediate Saturdays, Sundays, and legal holidays; and (C) include the last day of the period, but if the last day is a Saturday, Sunday, or legal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or legal holiday."Official source
- Brief extensions limited to one 30-day extension each for opening and responding briefs (21167.6(h)).
- If the clerk's office is closed or inaccessible on the last day (weather, emergency or local closure orders), the deadline may be extended. Check local orders.
This calculator applies the cited rules to the dates you enter. It is not legal advice. Court orders, local rules, and case-specific facts can change a deadline; verify before relying on it. Rule set pending attorney review.
Worked example
Date the notice designating the clerk's transcript was filed on Monday, March 15, 2027, personal service: due Friday, May 14, 2027.
- Trigger (Date the notice designating the clerk's transcript was filed): Monday, March 15, 2027.
- Exclude the trigger day and count 60 calendar days: Friday, May 14, 2027.
Notes
Brief extensions limited to one 30-day extension each for opening and responding briefs (21167.6(h)).
Related deadlines
- CEQA petition: 30 days after filing of Notice of Determination (EIR, negative declaration, other acts) (30 days after)
- CEQA petition challenging an exemption: 35 days after filing of Notice of Exemption (35 days after)
- CEQA petition: 180 days after project approval (or commencement) where no NOD/NOE filed or no determination made (180 days after)
- CEQA: personally serve record-preparation request and petition on agency within 10 business days of filing (10 business days after)
- CEQA: agency prepares and certifies record within 60 days after service of request (60 days after)
- CEQA: petitioner must request a hearing within 90 days of filing the petition (90 days after)
- CEQA: briefing to be completed within 90 days of the hearing request (absent good cause) (90 days after)
- CEQA: furnish copy of petition (and any amended or supplemental pleading) to the Attorney General within 10 days after filing (10 days after)
Rules current as of 2026-10-27. Confirm against the official source and any local rule or court order before relying on a date. Rules changelog.