CEQA: minimum public review period for draft EIR submitted to State Clearinghouse (state agency involvement or statewide/regional significance), 45 days

45 days after first day of the public review period, under Cal. Pub. Res. Code 21091(a).

Rule text

If the draft environmental impact report is for a proposed project where a state agency is the lead agency, a responsible agency, or a trustee agency; a state agency otherwise has jurisdiction by law with respect to the project; or the proposed project is of sufficient statewide, regional, or areawide significance ..., the review period shall be at least 45 days, and the lead agency shall provide the document ... to the State Clearinghouse

Cal. Pub. Res. Code 21091(a), official source

Calculate this deadline

Deadline
Monday, December 21, 2026
  1. Trigger (First day of the public review period): Friday, November 6, 2026.
  2. Exclude the trigger day and count 45 calendar days: Monday, December 21, 2026.
Rules applied
Cal. Pub. Res. Code 21091(a)
If the draft environmental impact report is for a proposed project where a state agency is the lead agency, a responsible agency, or a trustee agency; a state agency otherwise has jurisdiction by law with respect to the project; or the proposed project is of sufficient statewide, regional, or areawide significance ..., the review period shall be at least 45 days, and the lead agency shall provide the document ... to the State Clearinghouse
Official source
Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)
CCP 12: "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded." CCP 12a(a): "If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays." Gov. Code 6707: "When the last day for filing any instrument or other document with a state agency falls upon a Saturday or holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed." FRCP 6(a): "The following rules apply in computing any time period specified in these rules, in any local rule or court order, or in any statute that does not specify a method of computing time. (1) ... (A) exclude the day of the event that triggers the period; (B) count every day, including intermediate Saturdays, Sundays, and legal holidays; and (C) include the last day of the period, but if the last day is a Saturday, Sunday, or legal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or legal holiday."
Official source
  • State agency review day one is the date the Clearinghouse distributes the document (21091(c)(2)); shorter Clearinghouse review possible on request (21091(e)).
  • If the clerk's office is closed or inaccessible on the last day (weather, emergency or local closure orders), the deadline may be extended. Check local orders.

This calculator applies the cited rules to the dates you enter. It is not legal advice. Court orders, local rules, and case-specific facts can change a deadline; verify before relying on it. Rule set pending attorney review.

Worked example

First day of the public review period on Monday, March 15, 2027, personal service: due Thursday, April 29, 2027.

  1. Trigger (First day of the public review period): Monday, March 15, 2027.
  2. Exclude the trigger day and count 45 calendar days: Thursday, April 29, 2027.

Notes

State agency review day one is the date the Clearinghouse distributes the document (21091(c)(2)); shorter Clearinghouse review possible on request (21091(e)).

Related deadlines

All California pre-suit, housing and employment deadlines

Rules current as of 2026-10-27. Confirm against the official source and any local rule or court order before relying on a date. Rules changelog.