Specific plan residential exemption (Gov. Code 65457): action alleging a supplemental EIR was required, within 30 days of approval
30 days after date of the public agency's decision to carry out or approve the project, under Cal. Gov. Code 65457(b).
Rule text
(b) An action or proceeding alleging that a public agency has approved a project pursuant to a specific plan without having previously certified a supplemental environmental impact report for the specific plan, where required by subdivision (a), shall be commenced within 30 days of the public agency's decision to carry out or approve the project.
Calculate this deadline
Deadline
Monday, December 7, 2026
- Trigger (Date of the public agency's decision to carry out or approve the project): Friday, November 6, 2026.
- Exclude the trigger day and count 30 calendar days: Sunday, December 6, 2026.
- That day is a Sunday, so the deadline moves to the next court day: Monday, December 7, 2026 (Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)).
Rules applied
Cal. Gov. Code 65457(b)
(b) An action or proceeding alleging that a public agency has approved a project pursuant to a specific plan without having previously certified a supplemental environmental impact report for the specific plan, where required by subdivision (a), shall be commenced within 30 days of the public agency's decision to carry out or approve the project.Official source
Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)
CCP 12: "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded." CCP 12a(a): "If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays." Gov. Code 6707: "When the last day for filing any instrument or other document with a state agency falls upon a Saturday or holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed." FRCP 6(a): "The following rules apply in computing any time period specified in these rules, in any local rule or court order, or in any statute that does not specify a method of computing time. (1) ... (A) exclude the day of the event that triggers the period; (B) count every day, including intermediate Saturdays, Sundays, and legal holidays; and (C) include the last day of the period, but if the last day is a Saturday, Sunday, or legal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or legal holiday."Official source
- Runs from the decision, not from any notice.
- If the clerk's office is closed or inaccessible on the last day (weather, emergency or local closure orders), the deadline may be extended. Check local orders.
This calculator applies the cited rules to the dates you enter. It is not legal advice. Court orders, local rules, and case-specific facts can change a deadline; verify before relying on it. Rule set pending attorney review.
Worked example
Date of the public agency's decision to carry out or approve the project on Monday, March 15, 2027, personal service: due Wednesday, April 14, 2027.
- Trigger (Date of the public agency's decision to carry out or approve the project): Monday, March 15, 2027.
- Exclude the trigger day and count 30 calendar days: Wednesday, April 14, 2027.
Notes
Runs from the decision, not from any notice.
Related deadlines
- CEQA petition: 30 days after filing of Notice of Determination (EIR, negative declaration, other acts) (30 days after)
- CEQA petition challenging an exemption: 35 days after filing of Notice of Exemption (35 days after)
- CEQA petition: 180 days after project approval (or commencement) where no NOD/NOE filed or no determination made (180 days after)
- CEQA: personally serve record-preparation request and petition on agency within 10 business days of filing (10 business days after)
- CEQA: agency prepares and certifies record within 60 days after service of request (60 days after)
- CEQA: petitioner must request a hearing within 90 days of filing the petition (90 days after)
- CEQA: briefing to be completed within 90 days of the hearing request (absent good cause) (90 days after)
- CEQA: furnish copy of petition (and any amended or supplemental pleading) to the Attorney General within 10 days after filing (10 days after)
Rules current as of 2026-10-27. Confirm against the official source and any local rule or court order before relying on a date. Rules changelog.