Lemon law (CCP 871.21, opt-in manufacturers): outer limit, 6 years after original delivery of the vehicle

72 months after date of original delivery of the motor vehicle, under Cal. Code Civ. Proc. 871.21(b), (c).

Rule text

(b) Notwithstanding subdivision (a), an action covered by Section 871.20 shall not be brought later than six years after the date of original delivery of the motor vehicle.

Cal. Code Civ. Proc. 871.21(b), (c), official source

Calculate this deadline

Deadline
Monday, November 8, 2032
  1. Trigger (Date of original delivery of the motor vehicle): Friday, November 6, 2026.
  2. Add 72 months: Saturday, November 6, 2032.
  3. That day is a Saturday, so the deadline moves to the next court day: Monday, November 8, 2032 (Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)).
Rules applied
Cal. Code Civ. Proc. 871.21(b), (c)
(b) Notwithstanding subdivision (a), an action covered by Section 871.20 shall not be brought later than six years after the date of original delivery of the motor vehicle.
Official source
Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)
CCP 12: "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded." CCP 12a(a): "If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays." Gov. Code 6707: "When the last day for filing any instrument or other document with a state agency falls upon a Saturday or holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed." FRCP 6(a): "The following rules apply in computing any time period specified in these rules, in any local rule or court order, or in any statute that does not specify a method of computing time. (1) ... (A) exclude the day of the event that triggers the period; (B) count every day, including intermediate Saturdays, Sundays, and legal holidays; and (C) include the last day of the period, but if the last day is a Saturday, Sunday, or legal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or legal holiday."
Official source
  • 6 years = 72 months. Pair with lemon_871_21_sol_1yr_after_warranty and use the earlier date. 871.21(c) tolling applies to both periods (not modeled). OPT-IN ONLY: CCP 871.20-871.28 apply only to actions against a manufacturer that elected under CCP 871.29 (written notice to the DCA Arbitration Certification Program by October 31 of the preceding year, covering vehicles sold in five consecutive calendar years) or under CCP 871.30 (one-time election within 30 days of April 2, 2025, covering vehicles sold new in 2025 and prior years). Check the ACP's published list (871.29(c), 871.30(b)) and the notice given at sale (871.29(d)); the list itself was not verified here (outside the official-code source set). Applies only to restitution/replacement claims based on noncompliance with the applicable express warranty, not service contract claims (871.20).
  • If the clerk's office is closed or inaccessible on the last day (weather, emergency or local closure orders), the deadline may be extended. Check local orders.

This calculator applies the cited rules to the dates you enter. It is not legal advice. Court orders, local rules, and case-specific facts can change a deadline; verify before relying on it. Rule set pending attorney review.

Worked example

Date of original delivery of the motor vehicle on Monday, March 15, 2027, personal service: due Tuesday, March 15, 2033.

  1. Trigger (Date of original delivery of the motor vehicle): Monday, March 15, 2027.
  2. Add 72 months: Tuesday, March 15, 2033.

Notes

6 years = 72 months. Pair with lemon_871_21_sol_1yr_after_warranty and use the earlier date. 871.21(c) tolling applies to both periods (not modeled). OPT-IN ONLY: CCP 871.20-871.28 apply only to actions against a manufacturer that elected under CCP 871.29 (written notice to the DCA Arbitration Certification Program by October 31 of the preceding year, covering vehicles sold in five consecutive calendar years) or under CCP 871.30 (one-time election within 30 days of April 2, 2025, covering vehicles sold new in 2025 and prior years). Check the ACP's published list (871.29(c), 871.30(b)) and the notice given at sale (871.29(d)); the list itself was not verified here (outside the official-code source set). Applies only to restitution/replacement claims based on noncompliance with the applicable express warranty, not service contract claims (871.20).

Related deadlines

All California pre-suit, housing and employment deadlines

Rules current as of 2026-10-27. Confirm against the official source and any local rule or court order before relying on a date. Rules changelog.