Local agency claim over $50,000 up to $375,000: written response within 60 days of receipt (or documentation request within 30 days)

60 days after date the local agency received the claim, under Cal. Pub. Contract Code 20104.2(c)(1).

Rule text

For claims of over fifty thousand dollars ($50,000) and less than or equal to three hundred seventy-five thousand dollars ($375,000), the local agency shall respond in writing to all written claims within 60 days of receipt of the claim, or may request, in writing, within 30 days of receipt of the claim, any additional documentation supporting the claim or relating to defenses to the claim the local agency may have against the claimant.

Cal. Pub. Contract Code 20104.2(c)(1), official source

Calculate this deadline

Deadline
Tuesday, January 5, 2027
  1. Trigger (Date the local agency received the claim): Friday, November 6, 2026.
  2. Exclude the trigger day and count 60 calendar days: Tuesday, January 5, 2027.
Rules applied
Cal. Pub. Contract Code 20104.2(c)(1)
For claims of over fifty thousand dollars ($50,000) and less than or equal to three hundred seventy-five thousand dollars ($375,000), the local agency shall respond in writing to all written claims within 60 days of receipt of the claim, or may request, in writing, within 30 days of receipt of the claim, any additional documentation supporting the claim or relating to defenses to the claim the local agency may have against the claimant.
Official source
Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)
CCP 12: "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded." CCP 12a(a): "If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays." Gov. Code 6707: "When the last day for filing any instrument or other document with a state agency falls upon a Saturday or holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed." FRCP 6(a): "The following rules apply in computing any time period specified in these rules, in any local rule or court order, or in any statute that does not specify a method of computing time. (1) ... (A) exclude the day of the event that triggers the period; (B) count every day, including intermediate Saturdays, Sundays, and legal holidays; and (C) include the last day of the period, but if the last day is a Saturday, Sunday, or legal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or legal holiday."
Official source
  • Local agency public works claim (Pub. Contract Code 20104-20104.6; claims of $375,000 or less). After further documentation, response due within 30 days after receipt (or the time the claimant took, if greater) (c)(3).
  • If the clerk's office is closed or inaccessible on the last day (weather, emergency or local closure orders), the deadline may be extended. Check local orders.

This calculator applies the cited rules to the dates you enter. It is not legal advice. Court orders, local rules, and case-specific facts can change a deadline; verify before relying on it. Rule set pending attorney review.

Worked example

Date the local agency received the claim on Monday, March 15, 2027, personal service: due Friday, May 14, 2027.

  1. Trigger (Date the local agency received the claim): Monday, March 15, 2027.
  2. Exclude the trigger day and count 60 calendar days: Friday, May 14, 2027.

Unsettled points

  • The calculator shows a 45-day agency response for a claim of exactly $50,000, the earlier tier.Other reading: If the claim falls in the over-$50,000 tier, the agency has 60 days.

Notes

Local agency public works claim (Pub. Contract Code 20104-20104.6; claims of $375,000 or less). After further documentation, response due within 30 days after receipt (or the time the claimant took, if greater) (c)(3).

Related deadlines

All California pre-suit, housing and employment deadlines

Rules current as of 2026-10-27. Confirm against the official source and any local rule or court order before relying on a date. Rules changelog.