Public works payment bond: written notice to surety and principal within 15 days after recording of notice of completion (no preliminary notice given)
15 days after date the notice of completion was recorded, under Cal. Civ. Code 9560(b), (c).
Rule text
(b) If preliminary notice was not given as provided in Chapter 3 (commencing with Section 9300), a claimant may enforce a claim by giving written notice to the surety and the bond principal within 15 days after recordation of a notice of completion. If no notice of completion has been recorded, the time for giving written notice to the surety and the bond principal is extended to 75 days after completion of the work of improvement.
Calculate this deadline
- Trigger (Date the notice of completion was recorded): Friday, November 6, 2026.
- Exclude the trigger day and count 15 calendar days: Saturday, November 21, 2026.
- That day is a Saturday, so the deadline moves to the next court day: Monday, November 23, 2026 (Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)).
Cal. Civ. Code 9560(b), (c)
(b) If preliminary notice was not given as provided in Chapter 3 (commencing with Section 9300), a claimant may enforce a claim by giving written notice to the surety and the bond principal within 15 days after recordation of a notice of completion. If no notice of completion has been recorded, the time for giving written notice to the surety and the bond principal is extended to 75 days after completion of the work of improvement.Official source
Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)
CCP 12: "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded." CCP 12a(a): "If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays." Gov. Code 6707: "When the last day for filing any instrument or other document with a state agency falls upon a Saturday or holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed." FRCP 6(a): "The following rules apply in computing any time period specified in these rules, in any local rule or court order, or in any statute that does not specify a method of computing time. (1) ... (A) exclude the day of the event that triggers the period; (B) count every day, including intermediate Saturdays, Sundays, and legal holidays; and (C) include the last day of the period, but if the last day is a Saturday, Sunday, or legal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or legal holiday."Official source
- Alternative: pw_bond_notice_75_days_no_noc. Subdivision (c) applies the same 15/75-day periods to claimants with no direct contract with the contractor, with exceptions in (d). Not applicable to laborers (e).
- If the clerk's office is closed or inaccessible on the last day (weather, emergency or local closure orders), the deadline may be extended. Check local orders.
This calculator applies the cited rules to the dates you enter. It is not legal advice. Court orders, local rules, and case-specific facts can change a deadline; verify before relying on it. Rule set pending attorney review.
Worked example
Date the notice of completion was recorded on Monday, March 15, 2027, personal service: due Tuesday, March 30, 2027.
- Trigger (Date the notice of completion was recorded): Monday, March 15, 2027.
- Exclude the trigger day and count 15 calendar days: Tuesday, March 30, 2027.
Notes
Alternative: pw_bond_notice_75_days_no_noc. Subdivision (c) applies the same 15/75-day periods to claimants with no direct contract with the contractor, with exceptions in (d). Not applicable to laborers (e).
Related deadlines
- Mechanics lien (private works): preliminary notice within 20 days after first furnishing work (20 days after)
- Mechanics lien: direct contractor records claim of lien within 90 days after completion (no notice of completion/cessation recorded) (90 days after)
- Mechanics lien: direct contractor records claim of lien within 60 days after owner records notice of completion or cessation (60 days after)
- Mechanics lien: subcontractor/supplier/laborer records claim of lien within 90 days after completion (no notice recorded) (90 days after)
- Mechanics lien: subcontractor/supplier/laborer records claim of lien within 30 days after owner records notice of completion or cessation (30 days after)
- Owner may record notice of completion on or within 15 days after completion (15 days after)
- Owner gives copy of recorded notice of completion/cessation to direct contractor and preliminary-notice claimants within 10 days (10 days after)
- Mechanics lien: action to enforce (foreclose) lien within 90 days after recording claim of lien (90 days after)
Rules current as of 2026-10-27. Confirm against the official source and any local rule or court order before relying on a date. Rules changelog.