SB 800: builder's written offer to repair within 30 days of the initial (or second) inspection

30 days after date of the initial inspection or testing, or of the second inspection if one was requested, under Cal. Civ. Code 917; 920.

Rule text

917. Within 30 days of the initial or, if requested, second inspection or testing, the builder may offer in writing to repair the violation. ... 920. If the builder fails to make an offer to repair or otherwise strictly comply with this chapter within the times specified, the claimant is released from the requirements of this chapter and may proceed with the filing of an action.

Cal. Civ. Code 917; 920, official source

Calculate this deadline

Deadline
Sunday, December 6, 2026
  1. Trigger (Date of the initial inspection or testing, or of the second inspection if one was requested): Friday, November 6, 2026.
  2. Exclude the trigger day and count 30 calendar days: Sunday, December 6, 2026.
  3. That day is a Sunday, but this date is fixed by the rule and does not move: Sunday, December 6, 2026.
Rules applied
Cal. Civ. Code 917; 920
917. Within 30 days of the initial or, if requested, second inspection or testing, the builder may offer in writing to repair the violation. ... 920. If the builder fails to make an offer to repair or otherwise strictly comply with this chapter within the times specified, the claimant is released from the requirements of this chapter and may proceed with the filing of an action.
Official source
Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)
CCP 12: "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded." CCP 12a(a): "If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays." Gov. Code 6707: "When the last day for filing any instrument or other document with a state agency falls upon a Saturday or holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed." FRCP 6(a): "The following rules apply in computing any time period specified in these rules, in any local rule or court order, or in any statute that does not specify a method of computing time. (1) ... (A) exclude the day of the event that triggers the period; (B) count every day, including intermediate Saturdays, Sundays, and legal holidays; and (C) include the last day of the period, but if the last day is a Saturday, Sunday, or legal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or legal holiday."
Official source
  • Enter the second-inspection date if a second inspection was properly requested; otherwise the initial inspection date. The offer must be accompanied by an offer to mediate (919). A cash-only offer is permitted (929). Failure releases the claimant to sue (920). SB 800 applies only to new residential units where the purchase agreement was signed by the seller on or after January 1, 2003 (Civ. Code 938). Chapter 4 time periods 'are to be strictly construed' and may be extended only by mutual agreement evidenced by a postclaim written confirmation by the homeowner (Civ. Code 930(a)). If the builder elected its own alternative nonadversarial contractual procedure at the time of sale (Civ. Code 914(a)), these statutory periods do not apply.
  • If the clerk's office is closed or inaccessible on the last day (weather, emergency or local closure orders), the deadline may be extended. Check local orders.

This calculator applies the cited rules to the dates you enter. It is not legal advice. Court orders, local rules, and case-specific facts can change a deadline; verify before relying on it. Rule set pending attorney review.

Worked example

Date of the initial inspection or testing, or of the second inspection if one was requested on Monday, March 15, 2027, personal service: due Wednesday, April 14, 2027.

  1. Trigger (Date of the initial inspection or testing, or of the second inspection if one was requested): Monday, March 15, 2027.
  2. Exclude the trigger day and count 30 calendar days: Wednesday, April 14, 2027.

Notes

Enter the second-inspection date if a second inspection was properly requested; otherwise the initial inspection date. The offer must be accompanied by an offer to mediate (919). A cash-only offer is permitted (929). Failure releases the claimant to sue (920). SB 800 applies only to new residential units where the purchase agreement was signed by the seller on or after January 1, 2003 (Civ. Code 938). Chapter 4 time periods 'are to be strictly construed' and may be extended only by mutual agreement evidenced by a postclaim written confirmation by the homeowner (Civ. Code 930(a)). If the builder elected its own alternative nonadversarial contractual procedure at the time of sale (Civ. Code 914(a)), these statutory periods do not apply.

Related deadlines

All California pre-suit, housing and employment deadlines

Rules current as of 2026-10-27. Confirm against the official source and any local rule or court order before relying on a date. Rules changelog.