CASp safe harbor reuse after modifications: obtain additional CASp inspection within 30 days of final building department approval or certificate of occupancy
30 days after date of final approval by the building department or certificate of occupancy for the modification or alteration, under Cal. Civ. Code 55.56(g)(4).
Rule text
(4) A defendant may claim the protection from liability for minimum statutory damages under paragraph (3) only once for each structure or area inspected by a CASp, unless the inspected structure or area has undergone modifications or alterations that affect the compliance with construction-related accessibility standards of those structures or areas after the date of the last inspection, and the defendant obtains an additional CASp inspection within 30 days of final approval by the building department or certificate of occupancy, as appropriate, regarding the modification or alterations.
Calculate this deadline
- Trigger (Date of final approval by the building department or certificate of occupancy for the modification or alteration): Friday, November 6, 2026.
- Exclude the trigger day and count 30 calendar days: Sunday, December 6, 2026.
- That day is a Sunday, so the deadline moves to the next court day: Monday, December 7, 2026 (Cal. Code Civ. Proc. 12, 12a, 12b, 10; Cal. Rules of Court, rule 1.10).
Cal. Civ. Code 55.56(g)(4)
(4) A defendant may claim the protection from liability for minimum statutory damages under paragraph (3) only once for each structure or area inspected by a CASp, unless the inspected structure or area has undergone modifications or alterations that affect the compliance with construction-related accessibility standards of those structures or areas after the date of the last inspection, and the defendant obtains an additional CASp inspection within 30 days of final approval by the building department or certificate of occupancy, as appropriate, regarding the modification or alterations.Official source
Cal. Code Civ. Proc. 12, 12a, 12b, 10; Cal. Rules of Court, rule 1.10
CCP 12: "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded." CCP 12a(a): "If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays." CCP 12b: "If any city, county, state, or public office, other than a branch office, is closed for the whole of any day, insofar as the business of that office is concerned, that day shall be considered as a holiday for the purposes of computing time under Sections 12 and 12a." CCP 10: "Holidays within the meaning of this code are every Sunday and any other days that are specified or provided for as judicial holidays in Section 135."Official source
- Civ. Code 55.56 as amended by Stats. 2016, ch. 13 (SB 269), eff. May 10, 2016. NOTE: the damages-reduction provisions are in subdivision (g); 55.54 and 55.3 still cross-reference 'subdivision (f) of Section 55.56' (stale cross-reference left by SB 269's relettering).
- If the clerk's office is closed or inaccessible on the last day (weather, emergency or local closure orders), the deadline may be extended. Check local orders.
This calculator applies the cited rules to the dates you enter. It is not legal advice. Court orders, local rules, and case-specific facts can change a deadline; verify before relying on it. Rule set pending attorney review.
Worked example
Date of final approval by the building department or certificate of occupancy for the modification or alteration on Monday, March 15, 2027, personal service: due Wednesday, April 14, 2027.
- Trigger (Date of final approval by the building department or certificate of occupancy for the modification or alteration): Monday, March 15, 2027.
- Exclude the trigger day and count 30 calendar days: Wednesday, April 14, 2027.
Notes
Civ. Code 55.56 as amended by Stats. 2016, ch. 13 (SB 269), eff. May 10, 2016. NOTE: the damages-reduction provisions are in subdivision (g); 55.54 and 55.3 still cross-reference 'subdivision (f) of Section 55.56' (stale cross-reference left by SB 269's relettering).
Related deadlines
- Construction-related accessibility claim: defendant's application for stay and early evaluation conference (no later than first responsive pleading or appearance, normally 30 days after service of summons) (30 days after)
- Construction-related accessibility claim: application for stay and early evaluation conference after plaintiff (formerly in pro per) serves Notice of Substitution of Counsel (30 days) (30 days after)
- Early evaluation conference: court must set it no later than 70 days after issuing the stay order (70 days after)
- Early evaluation conference: may not be set earlier than 50 days after the defendant's application is filed (50 days after)
- Early evaluation conference: 90-day stay of the construction-related accessibility claim (expires) (90 days after)
- Early evaluation conference: qualified defendant files and serves CASp inspection report at least 15 days before the conference (15 days before)
- Early evaluation conference: plaintiff files and serves statement (itemized conditions, damages, fees, settlement demand) at least 15 days before the conference (15 days before)
- Early evaluation conference: joint site inspection at the premises (if defendant requested) no later than 30 days after the court order (30 days after)
Local rules by county
County local rules and courtroom procedures can add to or change this deadline. Pick a county to calculate with them applied.
- Alameda
- Alpine
- Amador
- Butte
- Calaveras
- Colusa
- Contra Costa
- Del Norte
- El Dorado
- Fresno
- Glenn
- Humboldt
- Imperial
- Inyo
- Kern
- Kings
- Lake
- Lassen
- Los Angeles
- Madera
- Marin
- Mariposa
- Mendocino
- Merced
- Modoc
- Mono
- Monterey
- Napa
- Nevada
- Orange
- Placer
- Plumas
- Riverside
- Sacramento
- San Benito
- San Bernardino
- San Diego
- San Francisco
- San Joaquin
- San Luis Obispo
- San Mateo
- Santa Barbara
- Santa Clara
- Santa Cruz
- Shasta
- Sierra
- Siskiyou
- Solano
- Sonoma
- Stanislaus
- Sutter
- Tehama
- Trinity
- Tulare
- Tuolumne
- Ventura
- Yolo
- Yuba
Rules current as of 2026-10-25. Confirm against the official source and any local rule or court order before relying on a date. Rules changelog.