Brown Act cure-or-correct demand: 30 days if action taken in open session but in violation of agenda requirements (Gov. Code 54954.2)

30 days after date the legislative body took the challenged action, under Cal. Gov. Code 54960.1(c)(1).

Rule text

(c) (1) The written demand shall be made within 90 days from the date the action was taken unless the action was taken in an open session but in violation of Section 54954.2, in which case the written demand shall be made within 30 days from the date the action was taken.

Cal. Gov. Code 54960.1(c)(1), official source

Calculate this deadline

Deadline
Monday, December 7, 2026
  1. Trigger (Date the legislative body took the challenged action): Friday, November 6, 2026.
  2. Exclude the trigger day and count 30 calendar days: Sunday, December 6, 2026.
  3. That day is a Sunday, so the deadline moves to the next court day: Monday, December 7, 2026 (Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)).
Rules applied
Cal. Gov. Code 54960.1(c)(1)
(c) (1) The written demand shall be made within 90 days from the date the action was taken unless the action was taken in an open session but in violation of Section 54954.2, in which case the written demand shall be made within 30 days from the date the action was taken.
Official source
Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)
CCP 12: "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded." CCP 12a(a): "If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays." Gov. Code 6707: "When the last day for filing any instrument or other document with a state agency falls upon a Saturday or holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed." FRCP 6(a): "The following rules apply in computing any time period specified in these rules, in any local rule or court order, or in any statute that does not specify a method of computing time. (1) ... (A) exclude the day of the event that triggers the period; (B) count every day, including intermediate Saturdays, Sundays, and legal holidays; and (C) include the last day of the period, but if the last day is a Saturday, Sunday, or legal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or legal holiday."
Official source
  • See brown_act_cure_demand_90_days.
  • If the clerk's office is closed or inaccessible on the last day (weather, emergency or local closure orders), the deadline may be extended. Check local orders.

This calculator applies the cited rules to the dates you enter. It is not legal advice. Court orders, local rules, and case-specific facts can change a deadline; verify before relying on it. Rule set pending attorney review.

Worked example

Date the legislative body took the challenged action on Monday, March 15, 2027, personal service: due Wednesday, April 14, 2027.

  1. Trigger (Date the legislative body took the challenged action): Monday, March 15, 2027.
  2. Exclude the trigger day and count 30 calendar days: Wednesday, April 14, 2027.

Notes

See brown_act_cure_demand_90_days.

Related deadlines

All California pre-suit, housing and employment deadlines

Rules current as of 2026-10-27. Confirm against the official source and any local rule or court order before relying on a date. Rules changelog.