Brown Act: commence action within 15 days of expiration of the 30-day cure period (alternative 2)
15 days after date the 30-day cure-or-correct period expired (see brown_act_cure_response_30_days), under Cal. Gov. Code 54960.1(c)(3), (4).
Rule text
(4) Within 15 days of receipt of the written notice of the legislative body’s decision to cure or correct, or not to cure or correct, or within 15 days of the expiration of the 30-day period to cure or correct, whichever is earlier, the demanding party shall be required to commence the action pursuant to subdivision (a) or thereafter be barred from commencing the action.
Calculate this deadline
- Trigger (Date the 30-day cure-or-correct period expired (see brown_act_cure_response_30_days)): Friday, November 6, 2026.
- Exclude the trigger day and count 15 calendar days: Saturday, November 21, 2026.
- That day is a Saturday, so the deadline moves to the next court day: Monday, November 23, 2026 (Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)).
Cal. Gov. Code 54960.1(c)(3), (4)
(4) Within 15 days of receipt of the written notice of the legislative body’s decision to cure or correct, or not to cure or correct, or within 15 days of the expiration of the 30-day period to cure or correct, whichever is earlier, the demanding party shall be required to commence the action pursuant to subdivision (a) or thereafter be barred from commencing the action.Official source
Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)
CCP 12: "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded." CCP 12a(a): "If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays." Gov. Code 6707: "When the last day for filing any instrument or other document with a state agency falls upon a Saturday or holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed." FRCP 6(a): "The following rules apply in computing any time period specified in these rules, in any local rule or court order, or in any statute that does not specify a method of computing time. (1) ... (A) exclude the day of the event that triggers the period; (B) count every day, including intermediate Saturdays, Sundays, and legal holidays; and (C) include the last day of the period, but if the last day is a Saturday, Sunday, or legal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or legal holiday."Official source
- See brown_act_suit_15_days_after_decision_notice; the EARLIER of the two dates controls. Enter the last day of the 30-day cure period as the trigger (the 15 days run from the day after it, 54960.1(c)(3)).
- If the clerk's office is closed or inaccessible on the last day (weather, emergency or local closure orders), the deadline may be extended. Check local orders.
This calculator applies the cited rules to the dates you enter. It is not legal advice. Court orders, local rules, and case-specific facts can change a deadline; verify before relying on it. Rule set pending attorney review.
Worked example
Date the 30-day cure-or-correct period expired (see brown_act_cure_response_30_days) on Monday, March 15, 2027, personal service: due Tuesday, March 30, 2027.
- Trigger (Date the 30-day cure-or-correct period expired (see brown_act_cure_response_30_days)): Monday, March 15, 2027.
- Exclude the trigger day and count 15 calendar days: Tuesday, March 30, 2027.
Notes
See brown_act_suit_15_days_after_decision_notice; the EARLIER of the two dates controls. Enter the last day of the 30-day cure period as the trigger (the 15 days run from the day after it, 54960.1(c)(3)).
Related deadlines
- Brown Act cure-or-correct demand (Gov. Code 54960.1): written demand within 90 days from date of action (90 days after)
- Brown Act cure-or-correct demand: 30 days if action taken in open session but in violation of agenda requirements (Gov. Code 54954.2) (30 days after)
- Brown Act: legislative body must cure/correct or decline in writing within 30 days of receipt of demand (inaction deemed refusal) (30 days after)
- Brown Act: commence action within 15 days of receipt of written notice of decision to cure or not cure (alternative 1) (15 days after)
- Brown Act past-practice challenge (Gov. Code 54960.2): submit cease and desist letter within 9 months of alleged violation (9 months after)
- Brown Act: legislative body may respond to cease and desist letter within 30 days of receiving it (30 days after)
- Brown Act past-practice suit: within 60 days of receipt of body's response (other than unconditional commitment) (alternative 1) (60 days after)
- Brown Act past-practice suit: within 60 days of expiration of the 30-day response period (alternative 2) (60 days after)
Rules current as of 2026-10-27. Confirm against the official source and any local rule or court order before relying on a date. Rules changelog.