Nonjudicial foreclosure (1-4 unit): after timely listing agreement, sale may not be conducted until an additional 45 days after the scheduled sale date

45 days after scheduled date of the trustee's sale (as it stood when the listing agreement was received), under Cal. Civ. Code 2924f(e)(1).

Rule text

... a sale of the property under the power of sale shall not be conducted until the expiration of an additional 45 days following the scheduled date of sale pursuant to subdivision (a) or (c) of Section 2924g if the trustee receives, at least five business days before the scheduled date of sale ... a listing agreement ...

Cal. Civ. Code 2924f(e)(1), official source

Calculate this deadline

Deadline
Tuesday, December 22, 2026
  1. Trigger (Scheduled date of the trustee's sale (as it stood when the listing agreement was received)): Friday, November 6, 2026.
  2. Exclude the trigger day and count 45 calendar days: Monday, December 21, 2026.
  3. The period includes its last day, so the earliest day to act is the next court day: Tuesday, December 22, 2026.
Rules applied
Cal. Civ. Code 2924f(e)(1)
... a sale of the property under the power of sale shall not be conducted until the expiration of an additional 45 days following the scheduled date of sale pursuant to subdivision (a) or (c) of Section 2924g if the trustee receives, at least five business days before the scheduled date of sale ... a listing agreement ...
Official source
Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)
CCP 12: "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded." CCP 12a(a): "If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays." Gov. Code 6707: "When the last day for filing any instrument or other document with a state agency falls upon a Saturday or holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed." FRCP 6(a): "The following rules apply in computing any time period specified in these rules, in any local rule or court order, or in any statute that does not specify a method of computing time. (1) ... (A) exclude the day of the event that triggers the period; (B) count every day, including intermediate Saturdays, Sundays, and legal holidays; and (C) include the last day of the period, but if the last day is a Saturday, Sunday, or legal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or legal holiday."
Official source
  • 'Until the expiration of an additional 45 days' read as: the earliest sale date is the day after day 45 is complete; computed date shown is day 45 (sale on the next business day or later is safest). See fc_listing_agreement_5_business_days_before_sale. Civ. Code 2924f version amended by Stats. 2025, ch. 200, sec. 7 (AB 1521), eff. Jan. 1, 2026, in effect until Jan. 1, 2031 (a different version, Stats. 2025, ch. 200, sec. 8, becomes operative Jan. 1, 2031; re-verify after that date).
  • If the clerk's office is closed or inaccessible on the last day (weather, emergency or local closure orders), the deadline may be extended. Check local orders.

This calculator applies the cited rules to the dates you enter. It is not legal advice. Court orders, local rules, and case-specific facts can change a deadline; verify before relying on it. Rule set pending attorney review.

Worked example

Scheduled date of the trustee's sale (as it stood when the listing agreement was received) on Monday, March 15, 2027, personal service: due Friday, April 30, 2027.

  1. Trigger (Scheduled date of the trustee's sale (as it stood when the listing agreement was received)): Monday, March 15, 2027.
  2. Exclude the trigger day and count 45 calendar days: Thursday, April 29, 2027.
  3. The period includes its last day, so the earliest day to act is the next court day: Friday, April 30, 2027.

Notes

'Until the expiration of an additional 45 days' read as: the earliest sale date is the day after day 45 is complete; computed date shown is day 45 (sale on the next business day or later is safest). See fc_listing_agreement_5_business_days_before_sale. Civ. Code 2924f version amended by Stats. 2025, ch. 200, sec. 7 (AB 1521), eff. Jan. 1, 2026, in effect until Jan. 1, 2031 (a different version, Stats. 2025, ch. 200, sec. 8, becomes operative Jan. 1, 2031; re-verify after that date).

Related deadlines

All California pre-suit, housing and employment deadlines

Rules current as of 2026-10-27. Confirm against the official source and any local rule or court order before relying on a date. Rules changelog.