Public works retention: public entity must release retention within 60 days after completion

60 days after date of completion of the work of improvement (as defined in 7107(c)), under Cal. Pub. Contract Code 7107(c).

Rule text

Within 60 days after the date of completion of the work of improvement, the retention withheld by the public entity shall be released.

Cal. Pub. Contract Code 7107(c), official source

Calculate this deadline

Deadline
Tuesday, January 5, 2027
  1. Trigger (Date of completion of the work of improvement (as defined in 7107(c))): Friday, November 6, 2026.
  2. Exclude the trigger day and count 60 calendar days: Tuesday, January 5, 2027.
Rules applied
Cal. Pub. Contract Code 7107(c)
Within 60 days after the date of completion of the work of improvement, the retention withheld by the public entity shall be released.
Official source
Cal. Code Civ. Proc. 12, 12a, 12b; Cal. Gov. Code 6800, 6707 (state agency filings); Fed. R. Civ. P. 6(a) (federal statutes and federal court filings)
CCP 12: "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded." CCP 12a(a): "If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays." Gov. Code 6707: "When the last day for filing any instrument or other document with a state agency falls upon a Saturday or holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed." FRCP 6(a): "The following rules apply in computing any time period specified in these rules, in any local rule or court order, or in any statute that does not specify a method of computing time. (1) ... (A) exclude the day of the event that triggers the period; (B) count every day, including intermediate Saturdays, Sundays, and legal holidays; and (C) include the last day of the period, but if the last day is a Saturday, Sunday, or legal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or legal holiday."
Official source
  • May withhold up to 150 percent of a disputed amount. State agencies holding 125 percent or less of remaining work value have 90 days (7107(g)). Late-release penalty provision (7107(f)) not quoted here.
  • If the clerk's office is closed or inaccessible on the last day (weather, emergency or local closure orders), the deadline may be extended. Check local orders.

This calculator applies the cited rules to the dates you enter. It is not legal advice. Court orders, local rules, and case-specific facts can change a deadline; verify before relying on it. Rule set pending attorney review.

Worked example

Date of completion of the work of improvement (as defined in 7107(c)) on Monday, March 15, 2027, personal service: due Friday, May 14, 2027.

  1. Trigger (Date of completion of the work of improvement (as defined in 7107(c))): Monday, March 15, 2027.
  2. Exclude the trigger day and count 60 calendar days: Friday, May 14, 2027.

Notes

May withhold up to 150 percent of a disputed amount. State agencies holding 125 percent or less of remaining work value have 90 days (7107(g)). Late-release penalty provision (7107(f)) not quoted here.